Wireup ngenea node and configure idrac
- Wire and configure iDrac
- Run 2 MPO cables from HPCR2R9
- Plug in and configure MPO and EDR connections
Activity
-
Newest first Oldest first
-
Show all activity Show comments only Show history only
- John-Paul Robinson added Sprint 22-15 label
added Sprint 22-15 label
- John-Paul Robinson assigned to @jpr
assigned to @jpr
- John-Paul Robinson assigned to @atlurie and unassigned @jpr
- John-Paul Robinson assigned to @jpr and unassigned @atlurie
- John-Paul Robinson changed milestone to %move remaining items from rust
changed milestone to %move remaining items from rust
- John-Paul Robinson changed time estimate to 4h
changed time estimate to 4h
- John-Paul Robinson changed title from Wireup ngenea node to Wireup ngenea node and configure idrac
changed title from Wireup ngenea node to Wireup ngenea node and configure idrac
- John-Paul Robinson changed the description
changed the description
- Ravi Tripathi added Sprint 22-16 label
added Sprint 22-16 label
- Author Owner
We have enough power clear in rack5 to turn on the ngenea node (est 500W). Current range is between 4.2-4.7kW. New is expected to be 4.7-5.2kW.
- Clyde Allan McClung added #96 as child task
added #96 as child task
- Clyde Allan McClung removed child task #96
removed child task #96
- Maintainer
The iDrac has been wired and configured (172.16.1.60).
2 MPO cables have been ran to r2r9. 100G optics are in the racks on both ends.
2 EDR cables are in r2r5. - Clyde Allan McClung changed the description
changed the description
- Clyde Allan McClung marked the checklist item Wire and configure iDrac as completed
marked the checklist item Wire and configure iDrac as completed
- Clyde Allan McClung marked the checklist item Run 2 MPO cables from HPCR2R9 as completed
marked the checklist item Run 2 MPO cables from HPCR2R9 as completed
- Ravi Tripathi added Sprint 22-17 label and removed Sprint 22-16 label
added Sprint 22-17 label and removed Sprint 22-16 label
- Ravi Tripathi added Sprint 22-16 label and removed Sprint 22-17 label
added Sprint 22-16 label and removed Sprint 22-17 label
- Ravi Tripathi added Sprint 22-17 label and removed Sprint 22-16 label
added Sprint 22-17 label and removed Sprint 22-16 label
- Ravi Tripathi removed Sprint 22-15 label
removed Sprint 22-15 label
- Clyde Allan McClung marked this issue as related to #143 (closed)
marked this issue as related to #143 (closed)
- Maintainer
The iDrac is configured. MPO and EDR wiring is in place and needs to be plugged in and configured: #143 (closed)
- Clyde Allan McClung closed
closed
- Clyde Allan McClung marked the checklist item Plug in and configure MPO and EDR connections as completed
marked the checklist item Plug in and configure MPO and EDR connections as completed
- Clyde Allan McClung mentioned in issue #167 (closed)
mentioned in issue #167 (closed)